[TPP-13] Assign Minter Role to Gov Infra Capped Minter

[TPP-13] Assign Minter Role to Gov Infra Capped Minter

:ballot_box: This proposal passed with a majority of ~965M ZK in-favor of the proposal. See final results here.

Title Proposal Title
Proposal Type TPP
One Sentence Summary Assign minter role from the Rate Limiter Mod to the Zk_Governance_Operations_2025 child capped minter, as outlined in TPP-11.
Proposal Author ZKsync Association
Proposal Sponsor Polar
Submitted onchain 2025-11-04
Version V1.0
Calldata Summary Assign minter role from the Rate Limiter Mod to the Zk_Governance_Operations_2025 child capped minter, as outlined in TPP-11.
Link to forum post [TPP-11] ZKsync Governance System Infrastructure Funding - #7 by rafa
Link to contracts Zk_Governance_RateLimit_2025: 0x8d03F20C213D435A8B50127DE3d5797845b2120D Zk_Governance_Operations_2025: 0x9e43647EF21194d6b4b29673DadeEC2688e6BA3D

Summary

This proposal assigns the Zk_Governance_Operations_2025 (Child Capped Minter) the minter role from the Zk_Governance_RateLimit_2025 (Rate Limit Modifier). This call is required to activate [TPP-11] ZKsync Governance System Infrastructure Funding.

Background

During post-execution verification of TPP-11, the Governance Team identified that the Zk_Governance_Operations_2025 capped minter contract was not granted the minter role from TPP-11’s Rate Limiter, which is controlled by the ZK Token Governor timelock. As a result, tokens are currently unable to be minted from the Zk_Governance_Operations_2025 capped minter.

Motivation

The Governance Infra System Funding program was approved in TPP-11 by the Token Assembly. There are no changes to the approved program design, motive or mechanic.

Program Mechanics

This proposal assigns minting rights from the Rate Limiter Mod to the Zk_Governance_Operations_2025 child capped minter, as outlined in TPP-11.

Capped Minter Smart-Contract Address Smart-Contract Admin Role Smart-Contract Minter Role Smart-Contract Pauser Role Minting Start Minting End Token Configuration Parameters
Zk_Governance_RateLimit_2025 (Rate Limit Modifier) 0x8d03F20C213D435A8B50127DE3d5797845b2120D Token Governor Timelock Zk_Governance_Operations_2025 Security Council via Parent Capped Minter n/a n/a Rate Limit: 8M ZK per month
Zk_Governance_Operations_2025 (Child Capped Minter) 0x9e43647EF21194d6b4b29673DadeEC2688e6BA3D ZKsync Association Governance Team 4/7 Multisig (0x6162BEfaaf5C2598dD92087A5a479b10b135275a) Child Capped Minters for Service Providers Security Council via Parent Capped Minter October 3, 2025 December 31, 2026 Cap: 33,000,000 ZK

Calldata to be executed:

  • Grant minter role from Zk_Governance_RateLimit_2025 to Zk_Governance_Operations_2025
2 Likes

:zap:TPP-13 Submitted Onchain

[TPP-13] Assign Minter Role to Gov Infra Capped Minter was submitted onchain. Pending a 7 day delay, voting for TPP-11 will open on Wednesday, November 12th at ~09:55 UTC.

:link: See onchain proposal here: ZKsync | [TPP-13] Assign Minter Role to Gov Infra Capped Minter

The following reflects the views of L2BEAT’s governance team, composed of @kaereste and @Manugotsuka, and it’s based on their combined research, fact-checking, and ideation.

We voted FOR.

It is a straightforward corrective step to activate the governance infrastructure funding that has already been approved in the TPP-11. The proposal only grants the missing minter permission from the rate limiter to the operations minter, leaving the 33M ZK cap, the 8M ZK monthly rate limit, and all oversight roles exactly as the DAO approved.

Given the narrow scope and the need to unblock contracted work, this is a sensible housekeeping fix. As a best practice, we recommend that the team publish a short post-execution verification with TX links to confirm that no additional role changes were included.